The “Car Body” which includes the engine and winches.
|

The “Boom Foot.” The 300 ton Liebherr breaks down to 16 semi loads for transport.
|
|

12.6 ton counterweight.
|

Second “crawler” track.
|
|

“Boom Head."
|

The “hook block” for the crane.
|
|

Liebherr crane "crawler" track transported from Kahului harbor.
|

Reverend Lee blessing the equipment, and all components of the project, especially the men and women working on the project.
|
|

The Liebherr getting ready to “crawl.”
|

The crane resting on “crane mats,” large timbers used to ensure the crane has a stable surface from which to work.
|
|

Boom down as high winds buffet the site.
|

Getting ready to “lift” one of the upper tower sections.
|
|

Upper tower section held in place while crews torque connecting bolts.
|

Boom extending over 200 feet in the air.
|